|
Introduction
Hospet
Steels Limited is a 300,000 TPA integrated alloy steel plant situated
at Ginigera, Dist: Koppal in North Karnataka. The Plant has been jointly
put up by M/s.Mukand Limited and Kalyani Steels Limited & was commissioned
in 1998.
The main facilities
at Hospet Steels Limited are:
- Iron ore mines
at Subbarayanahalli and Jambunathanahalli.
- Two Mini Blast
Furnaces of 250 M3 volume.
- Steel Melt Shop
comprising of EOF, Ladle Furnaces, Vacuum Degassing unit, billet and
bloom casters.
- 2 Hi Reversible
Blooming Mill.
This is a latest state
of the Art Steel Plant with high level of automation.
Total work force is
700 employees. The plant is running at rated capacity.
Steel making through
liquid pig iron route was envisaged since long in view of the ever-increasing
power tariff coupled with scarcity & high cost of scrap of appropriate
quality.
The need for high
productive rates on one hand & the stringent quality requirements,
applicable to alloy special steels on the other, was largely responsible
for opting the MBF- EOF route for steel production, a challenging proposition
since it would be the first plant in the world to do so.
Today the EOF route
at Hospet Steels Limited has emerged successfully to be the largest alloy
steel production facility in India & the only one amongst the four
operating in the world to have successfully adopted it to manufacture
alloys steels.
The wide spectrum
of grades ranges from very low alloy electrode grade to highly sophisticated
forging quality grades, bearing steels & micro alloyed steels etc.
With the twin-shell
system, it is possible to melt down and subsequently to refine and finish
heats with high chromium content in a continuous manner and under optimum
conditions.
High productivity
reflects in the reduced tapping weight and the resulting smaller and cheaper
equipment. This fact reduces significantly plant and building-related
effort and costs.
The CONARC 88t process,
carried out under industrial conditions, is a unique and the first process
for stainless steel, which combines properties of an electric arc furnace
and a converter. Clear metallurgical treatments supported with suitable
process control lead in combination with in down stream placed VOD plant
or an AOD converter to production of steel quality with decidedly better
characteristics. It concerns especially cleanness of the metal in view
on residual tramp elements.
High input of experiences
and know-how in the common development of this technology by TK A8T and
ACE81TA 8.A., market leaders in the production of flat stainless steel
products, ensures success in their application.
In summary one can
be stated, that the new production line allows stainless steel production
with highest level of productivity at significant lower production and
investment costs.
The CONARC SSt process completes the family of stainless steel processes
and run out far in the future with its modern technological properties.
Operations:
The EOF offers distinct advantage in terms of the charge input comprising
of 80% Hot Metal at 1300°C & 20% solid scrap. This ratio can be
flexibly altered upto 30% solid scrap based on the permissible heat balance
& the in-built scrap preheating facility.
A standardized operating
regime renders predictable decarburising rate made possible by the immense
stirring energy & high O2 efficiency by the submerged tuyeres. This
becomes a powerful means to achieve 'catch carbon' practice leading to
low [O] potential bath for downstream refining.
The submerged tap
hole and fast tilt back mechanism in conjunction with alloy feeding during
tapping offers minimal carryover slag and good primary deoxidation.
The typical construction
of the EOF, a combination of an Arc furnace & a converter makes continuous
slag flushing possible without blowing interruptions for deslagging. Thus
initial dephosporisation rate is high & the low basicity slag is flushed
out of the system very early in the blowing cycle, thereby enabling 'P'
levels of <0.010%.
The typical blow time
in the EOF is 32-35 min, with possibility of further reduction to 25 min
by means of usage of supersonic lance, enabling a productivity of 45-50
MT per hour.
Maintenance:
The short cycle blow
time though necessary is not obviously a sufficient condition to move
towards high productivity rate without ensuring high equipment availability.
Maintaining more than
105 water-cooled elements was a critical activity. The excessive down
time due to frequent water leakages & the safety hazards thereof were
major hindrance. Poor refractory life of meager 300 heats forced two shut
downs of 36 hours each per month for hearth change over, causing enormous
loss of production time.
- This was over come
by reducing the tuyere pipe internal diameter from 16 mm to 14 mm.
- Systematic maintenance
of tuyere length & timely repair of refractory around the tuyere
zone.
- Elimination of
water leakage in the furnace.
Water leakages were
minimized by introduction of spare shell thus providing ample time for
the maintenance of the water-cooled panels of the spare bottom during
it's idle time at home position. This resulted into increased refractory
life of 650+ heats consistently.
Punctual preventive
maintenance schedules helped in maintaining the health of the Gas Cleaning
Plant (GCP) systems, the heart of the EOF operations. The system now runs
in safe operating conditions with out interruptions.
In house innovations
in the venturi scrubber unit of the GCP has enabled precise control of
the furnace operating pressures, thereby minimizing Iron losses and improving
the metallic yields.
Metallurgical Achievements
- Successful deployment
of EOF for high productivity Alloy Special Steel production.
- High conversion
ratio of Hot metal to steel without use of mixture an intermediate storage
unit. Ultrasonic Soundness at 2:1 reduction ratio in High Temperature
boiler tubes.
- Banding controlled
within 30 microns in low alloy steel.
- Sound bloom macro
to produce crank shaft quality alloy steel for OEMs with reduction ratio
of 5:1. Development of High Nitrogen micro alloy steel for crank shaft
application for M/s Ford Motor Co. USA
- Development of
CHQ Steel through Billet Caster.
- IBR self-certification
achieved.
- ISO 9001: 2000
accreditation.
- ISO 14001:1996
accreditation.
Conclusion:
The MBF EOF route
for steel making at Hospet Steels Limited has proved extremely cost effective
largely due to:
- Low cost of Iron
Ore due to its locational advantage.
- High percentage
of charge input being low cost liquid pig iron.
- Power consumption
for primary steel production is mere 33 KWH/T.
- High productivity.
The EOF at Hospet
Steels Limited has established the capability of producing 28,000 MT per
month of finished steel blooms. This trend should surpass more than 100%
utilization of the installed capacity with the capability of meeting the
most stringent quality standards.
Hospet Steels Ltd
has undertaken projects to step up to 400000TPA within next financial
year (2004 2005).
|