|
Summary
Compared with the
traditional hot metal production via the blast furnace route, only the
COREX process offers the possibility to produce hot metal without BF quality
coke on industrial scale. The operation results achieved from the operating
COREX plants at POSCO, SALDANHA and jINDAL confirm this.
Together with POSCO
and RIST, both Korea, VAI currently is developing the FINEX process, a
smelting reduction process based on direct charging of coal and fine ore
in form of sinter feed. In May 2003 the FlNEX Demonstration plant with
an annual nominal capacity of 600,000 t hot metal commenced operations.
Based on the successful results, VAI was awarded a contract for the design
of the first industrial FlNEX 1.5M plant with an annual capacity of 1,500,000
t of hot metal at POSCO Pohang Works
All COREX developments
of the last years aim at the optimization of the process, the increase
of the productivity and the reduction of the specific consumption values.
The developments done are mainly carried out in the field of coal and
DRl charging into the melter gasifier, the charging of the burden, the
injection of the reduction gases to the reduction shaft and the preparation
of the raw materials. Specific notice was laid at the reduction of the
specific coke consumption. Based on some of the new developments a nearly
coke-free operation could be achieved at COREX/FINEX POSCO.
Status of the COREX
Projects
SALDANHA STEEL,
Saldanha Works, South Africa
An Integrated Compact
Mill (ICM), based on a COREX C-2000 unit in combination with a COREX Gas
based Direct Reduction (DR) Plant, was started-up in mid I 999 at SALDANHA
STEEL, on the west coast of South Africa.
Export gas from the
COREX plant is used for the production of direct reduced iron (DRI) in
an adjacent DR plant using a MIDREXTM shaft furnace and LINDE Vacuum Pressure
Swing Absorption plant (VPSA) for the removal of CO2. The DR plant is
operated with a mixture of about 65 per cent SISHEN lump ore and 35 per
cent CVRD pellets.
Both the hot metal
from the COREX plant and DRI from the DR plant are processed to high-quality
steel in a twin-shell EAF, followed by thin slab casting and direct rolling
to produce high-quality hot rolled coils (HRC).
Roughly 50 per cent
of the produced HRC are exported and 50 per cent are cold-rolled and further
treated at DUFERCO STEEL PROCESSING, an adjacent cold-rolling complex
also built by VAI on a turnkey basis. The cold-rolled coils are sold on
domestic and international markets.
The COREX plant at
SALDANHA STEEL was started up on December 1998 and is operated with mainly
indigenous iron ores comprising SISHEN lump ore (80 - 100%), CVRD pellets
(0 - 20%) and indigenous coal from the VAN DIJKSDRIFT and GROOTELUK coal
districts. All of the required additives are also supplied locally.
The highlights of
COREX/DR SALDANHA for 2004 (based on the production up to September 2004)
are:
-
Uninterrupted
production output of approx 750,000 tons of hot metal for 2004 (forecast).
-
Daily average
production rate of 2,300 t (approx. 15% above nominal capacity or
an increase of the average daily output compared to 2003 of approx.
plus 200 t/d
-
Plant availability
(calendar utilization) of more than 92.5%
-
A Reliable supply
of gas to a COREX-gas-based DR plant, yielding in a production output
of
700,000 tonnes of DRI
-
Longest continuous
uninterrupted operation 63 days
-
Recovery in excess
of 95% of all COREX slag sent to a slag granulation plant and sold
to the cement industry
-
Recycling of all
available mill scale, roller-hearth-furnace steel scale and DR-plant
classifier sands, as a COREX burden feedstock
-
Recovery of all
COREX, DR-plant, and steel-plant dust and sludge sent to a sludge
granulation plant and used in the manufacture of cement
During the last twelve
months the COREX plant achieved the following records:
The stability of the
SALDANHA STEEL COREX plant played a major role in SALDANHA STEEL's achievement
of 100% design capacity (1.25 mt HRC) production during the past year.
Jindal Vijayanagar
Steel, Toranagallu Works, India
Please allow to quote
out of a press release of JINDAL itself: [...] Realizing the importance
of environment protection, resource conservation and sustainable development
in a resource crunch country like India, the promoters of JINDAL VIJAYANAGAR
Steel Ltd. has adopted COREX iron making technology in its integrated
process route in India and is a leading technology steel producer. Two
C-2000 modules of COREX are in operation in JVSL. Module-l was commissioned
in August 1999 and Module-2 was commissioned in April 2001. This process
has greater flexibility in operation, uses various types of non-coking
coals as a primary fuel and requires raw materials of less stringent quality.
The gas generated from the process is used for power generation, for the
pellet plant and as a fuel in the integrated plant complex. The special
features of COREX hot metal are high temperature (1480 - 1510o C), low
sulphur, low nitrogen and least amount of impurities. Finally, it is more
eco-friendly compared to the conventional Blast Furnace route due to exclusion
of sinter plant and coke ovens.
A total of 6,544,798
tons (3,810,507 tons from Module-l and 2,734,291 tons from Module-2) of
hot metal was tapped from the time the plants were started up until the
end of September 2004. The furnaces achieved the following performance
during the last twelve months:
-
Reliable uninterrupted
production output of approx. 1,600,000 tons of hot metal
-
Typical plant
availability (calendar utilization) of 92.5%
-
Average specific
fuel and oxygen 1050 kg/t HM and 540 Nm3/t HM
-
Reliable gas supply
to power plant and as a fuel in the integrated plant complex.
-
Recovery in excess
of 94 per cent of COREX slag sent to slag granulation plant and used
in the manufacture of cement.
-
Recycling of most
of the metallurgical waste j such as coke fines, mill scale, iron
ore fines, LD Slag, limestone and dolomite fines etc as a COREX burden
feedstock.
-
During the last
twelve months, the COREX plants achieved the following records:
-
Highest monthly
throughput of hot metal 77516 tons from Module 2.
Highest monthly plant
calendar utilization 99.36% in Module 1 and 95.85% in Module 2.
Lowest monthly specific
fuel and oxygen consumption - fuel rate 945 kg/t HM and oxygen rate 492
Nm3 /t HM in Module 1 and fuel rate 970 kg/t HM and oxygen rate 510 Nm3/t
HM in Module 2.
JVSL has got certain
unique operational features like various fines addition directly into
the melter gasifier, recycling of various metallurgical wastes to an extent,
high melting rate operation etc. JVSL COREX has surpassed its rated capacity
by about 15 - 20 per cent, producing quality hot metal for steel making.
However, with increasing operational experiences in COREX, a number of
areas have been uncovered, where there are still possibilities of improvement
in terms of productivity, equipment availability and reduction in hot
metal cost [...].
POSCO, Pohang Works,
Republic of Korea
The COREX plant at
POSCO Pohang Works, Republic of Korea, which started up in 1995 adjacent
to the five existing blast furnaces, has since produced approximately
5.7 million tons of high-quality hot metal (as of September 2004) and
is operated since May 2003 in "FINEX process mode".
The FINEX Process
The FINEX Process,
a smelting-reduction technology based on the direct use of coal and fine
ore is now jointly developed by POSCO and VAL The direct use of fine ore
for the production of hot metal and DRI will be one of the driving forces
behind future developments.
COREX Coals
A wide range of non-coking
coals can be used in the COREX process. If these requirements for COREX
coals are compared to the requirements for blast furnace coals, it can
be concluded that the requirements are lower. COREX coals are more available
and it does not have to be emphasized that the use of more widely available
and thus lower cost coals lead to lower cost operations. Currently, this
is of high importance as metallurgical coal can only be secured on the
world market at increased prices due to non-availability, whereas "COREX"
coal prices kept widely constant during the last year. The price gap between
COREX@ coal price and metallurgical coal price that have been traded internationally
has opened from approximately 20 USD/t to approx. 35 USD/t.
Coke Consumption
All developments over
the last years aimed to optimize the process, increase the production
and to minimize the consumption figures. Special attention was put on
the coke consumption. Whereas P~SCO showed that it is possible to operate
the COREX plant at zero coke for long periods (coke consumption in total
1999 in average 19 kg/t HM) by a careful operation and treatment of the
raw materials, SALDANHA and JINDAL could not do similar for different
reasons. However, still ongoing developments on the process and on related
equipment resulted in coke quantities in the operating plants in the range
of approximately 2-10 % of the coal charge. As not all the developments
currently available could be implemented effectively in the operating
COREX plants (e.g. material distribution equipment) this figure will considerably
drop in future COREX plants.
Another important
aspect has to be taken into account regarding to the required coke quality:
In case coke is charged to the COREX plant, the coke quality is different
to the coke qualities as being typically used in the blast furnace. In
terms of blast furnace operation, only low quality coke is required for
COREX, which has also a tremendous effect to the specific coke price.
It is equal to coke breeze.
Finally, coke can
be seen as an "additive" for the process to be only a minor
economical issue as to the most extent thermal coal is directly used.
Latest Equipment Developments/
Optimizations in the COREX Process
Equipment Changes
Based on the experience
of the producing COREX plants that are operated at very different conditions
regarding raw material input and process control and on the experience
from the in-house blast furnace know-how, many investigations (e.g. CFD
calculations that show the tendencies and effects after implementation
of certain charging equipment) were carried out regarding the distribution
of the materials charged to the melter gasifier. Two major optimization
points were identified: charging of DRI to the melter gasifier and charging
of coal to the me Iter gasifier. Based on the results of the investigations
new equipment is designed and applied at single operating COREX plants
and will be applied in future COREX plants.
Installation of new DRI distribution
device
This new DRI distribution
system that is already installed at the COREX. SALDANHA plant (Figure
9) is to distribute the DRI evenly onto the melter-gasifier bed surface
in a "doughnut" form, at a radius of 2 m to 4 m from the center.
Tests during stable production indicated that the DRI flaps have a dramatic
effect on melter performance. When the -deflection flaps were moved away
from the DRI stream, an almost immediate deterioration in melter performance
was observed and stave heat losses peaked. Coke addition had to be increased
during the tests by 4% to maintain liquid iron temperature.
After the first start-ups
of the COREX plants at SALDANHA and JINDAL it was found that charging
of coal did not take place as desired. Due to the horizontal discharge
speed of the coal at the coal screw outlet, the main coal stream was placed
approximately 1 m off the center on the top of the char bed in the melter
gasifier. By centralizing the coal stream, the situation improved.
Due to the fact that
the coal was charged in one stream and no coal distribution took place,
major volumes of not-pyrolised coal came into hot areas of the melter
gasifier resulting in pressure peaks. After installing a static coal distribution
device (coal riffler), that distributed the coal over a wider area of
the char bed surface, the pressure peaks situation improved considerably.
Based on an almost pressure peak free operation the process pressure and
the char bed height could be increased resulting in a more stable hot
metal temperature and composition, leading to decreased specific consumption
values and smoother process operation.
Already the static
coal distribution improves the coal distribution. An even better result
will be achieved with a dynamic coal distribution system at COREX SALDANHA
that looks similar to a rotating chute of the blast furnace. Such a system
will be installed at SALDANHA to achieve a distribution.
Raw Material Preparation
Changes
Based on the fact
that COREX charges mainly lumpy coal into the process, also applications
for fine coal generated during the coal transport and storage had to be
found. Besides charging fine coal to a certain percentage directly into
the COREX melter gasifier, or using it in the coke oven process, in a
power plant or cement plant, at POSCO a coal briquetting technology was
also developed that suited for the COREX process.
During charging higher
amounts of briquettes, it was found that in case the briquettes contain
certain amounts of metallurgical coal, these briquettes supported a coke
free COREX@ operatio~. This fact is of importance. As the above-mentioned
equipment measures (distribution issues) that have already shown at SALDANHA
a considerably improved operation, are not all yet applied at COREX POSCO.
Conclusion
Based on the experience
of the four operating COREX plants and the 10 years of operational experience
of the ISCOR COREX* C-I000 Plant, a considerable knowledge base has been
accumulated with respect to engineering and operation. This knowledge
and subsequent investigations result in a most competitive hot metal production
compared with the blast-furnace route.
As the development
optimization of COREX technology is still underway, additional economical
and technological potentials are anticipated. Major developments are currently
carried out at the material distribution devices for charging of these
materials into the main aggregates of the COREX process - the melter gasifier
and the reduction shaft. Due to the well-proven plant concept, new process
features and the highly competitive production costs, VAI is confident
that the COREX Process will account for an increasing share of future
investments in iron making facilities.
As a consequence of
a tight raw material supply for the blast furnace, the COREX process enables
operators to produce hot metal based on raw materials that are still not
tight in supply and are available at "reasonable" prices.
The FINEX Process
is under development and will provide hot metal production based on the
direct use of coal and fine ore. Currently the COREX plant of POSCO is
part of the FINEX Demonstration Plant with an annual nominal hot metal
capacity of 600,000 t/a. The next step in the development will be the
design and erection of the FINEX 1.5M plant with an annual capacity of
1.5 million t/a hot metal. The direct use of fine ore for the production
of hot metal and DRI will be one of the driving forces behind future developments.
|