|
Corex Process - One of
the dynamic routes for gel making with special reference to the success
of JVSL
|
|
|
Dr S K Gupta
Dr S S Gupta
|
|
| ABSTRACT |
|
|
Research and Development work is being
carried out in different countries for last several decades to develop
alternative routes to iron making. The reason for such development comes
from the fact that the conventional route of Blast furnace iron making
uses metallurgical coal, which is scarce. Also because of associated sinter
plant and coke oven, the route has become highly capital intensive to
make its environment friendly. Smelting reduction is an emerging technology
for making hot iron using non-coking. Till today various smelting reduction
processes like CORER, ROMELT, HISMELT, DIOS, AUSMELT etc. have been developed
of which COREX is the first and so far only commercially established smelting
reduction process, which is developed by Voest Alpine Industrianlagenbau
(VAI), Austria. The stable and highly successfull operation of four COREX
plants (POSCO, Korea, JVSL, India, SALDANHA, South Africa) confirms that
COREX process is a proven and viable alternative to conventional blast
furnace technology.
|
|
| INTRODUCTION |
| |
|
In the world, the chief source of metallic iron today
is through Blast furnace, as the technology is most established, energy
efficient, and versatile both technologically and economically. However
due to the metallurgical coal to produce BF grade coke, and setting up
of coke ovens which pollutes the environment with its NOx and SOx emissions,
and rigid quality BF has become highly capital intensive. The economic,
environmental and cost pressures led to the development of Smelting-Reduction
processes like COREX, ROMELT, HISMELT, DIOS, AUSMELT etc. COREX is the
only Smelting-Reduction process so far commercialised and in India has
been adopted by Jindal Vijayanagar Steel Limited.
|
| |
| COREX PROCESS |
| |
|
COREX consists of two reactors, the reduction shaft and
the melter-gasifier. The reduction shaft is placed above the melter-gasifier
and reduced iron bearing material descends by gravity. The volume of the
reduction shaft and the melter-gasifier is about 600 m3 and 2200 m3 respectively.
|
| |
| Reduction Shaft |
| |
|
Iron ore, pellets and additives (limestone and dolomite)
are continuously charged into the reduction shaft via lock hopper system
located on the top of the shaft. Some amount of coke is also added to
the shaft to avoid clustering of the burden inside the shaft due to sticking
of ore/pellets and to maintain adequate bed permeability. The reduction
gas is injected through the bustle located about 5 meters above the bottom
of the shaft at 850oC and over 3-bar pressure. The specific reduction
gas flow is about 1200Nm3/ton of iron bearing burden charged to the shaft.
The gas moves in the counter current direction to the top of the shaft
and exits from the shaft at around 250oC. The iron bearing material gets
reduced to over 95% metallization in the shaft and is termed as DRI. Subsequently,
six screws discharge the DRI from the reduction shaft into the melter-gasifier.
The metallization degree of the DRI and the calcination of the additives
are strongly dependent on the following parameters l, 2:
- Amount and quality of the reduction gas flow
- Temperature of the reduction gas
- Reducibility of the iron bearing burden
- Average particle size and the distribution of the
solids charged
|
| Melter-Gasifier |
|
The melter-gasifier can largely be divided into three
reaction zones
- Gaseous free board zone (upper part or dome)
- Char bed (middle part above oxygen tuyeres)
- Hearth zone (lower part below oxygen tuyeres)
Due to continuous gas flow through the char bed,
there also exists a fluidized bed in the transition area between the char
bed and the free board zone. The hot DRI at around 600-800oC along with
partially calcined limestone and dolomite are continuously fed into the
melter-gasifier through DRI down pipes. The DRI down pipes are uniformly
distributed along the circumference near the top of the melter-gasifier
so as to ensure uniform distribution of material over the char bed. Additionally
non-coking coal, quartzite and required quantity of coke are continuously
charged by means of lock hopper system. The operating pressure, in the
melter-gasifier is in excess of 3 bars. Oxygen plays a vital role in COREX
process for generation of heat and reduction gases. It is injected through
the tuyeres, which gasifies the coal char generates CO. The hot gases
ascend upward through the char bed. The sensible heat of the gases is
transferred to the char bed, which is utilized for melting iron and slag
and other metallurgical reactions. The hot metal and slag are collected
in the hearth. The efficiency of the furnace depends largely on the distribution
of this gas in the char bed and utilization of the sensible heat of the
gas. The dome temperature maintained between maintained between 10OOoC
to 11OOoC, which assures cracking of all the volatile matter releases
from the coal. The gas generated inside the melter-gasifier contains fine
dust particles, which are separated in hot gas cyclones. The dust collected
in the cyclones is recycled back to the melter-gasifier through the dust
burners, where the dust is combusted with additional oxygen injected through
the burners. There are four such dust burners located around the circumference
of the melter-gasifier above the char bed. The gas from the melter-gasifier
is cooled to the reduction gas temperature (850oC) through the addition
of cooling gas. A major part of this gas is subsequently fed to the reduction
shaft. The excess gas is used to control the plant pressure. This excess
gas and the reduction shaft top gas are mixed prior to the take over point
and is termed as COREX export gas l, 2,4.
|
| The efficiency of the CORER process
depends on the following parameters: |
- Size and chemical analysis of the raw especially
the coal
- Low C02 percentage in the reduction gas so as to
ensure higher metallization of the DRI
- Optimum distribution of oxygen between the tuyeres
and dust burners
- Permeability of the char bed
- High system pressure
- Higher melting rate operation
|
Table 1 gives the comparison of JSVL,
Posco and Saldanha
|
Plant
|
JVSL
|
POSCO
|
SALDANAH
|
|
Corex-1
|
Corex-2
|
Total
|
|
Production, tonnes
|
797969
|
826475
|
1624444
|
626931
|
707002
|
|
Annualised Melting rate, t/hr
|
91.09
|
94.35
|
92.72
|
71.57
|
80.71
|
|
Fuel Rate, Kg/thm
|
1004
|
1005
|
1005
|
1154
|
1122
|
|
| |
Table 2 shows the
progress of COREX performance in JVSL
|
Year
|
Production, mt
|
Sp.Fuel consumption, kg/thm
|
Hot metal Temp., C
|
`Si', %
|
`S', %
|
|
1999-2000
|
0.40
|
1163
|
1491
|
0.75
|
0.060
|
|
2000-2001
|
0.77
|
1071
|
1503
|
0.66
|
0.037
|
|
2001-2002
|
1.52
|
1082
|
1497
|
0.58
|
0.037
|
|
2002-2003
|
1.46
|
1041
|
1497
|
0.71
|
0.029
|
|
2004-2003
(Till Jan' 04)
|
1.36
|
1000
|
1487
|
0.76
|
0.027
|
|
|
| RESULTS AND DISCUSSION |
|
Samples were taken from each stage
of production. One test piece was cast from each heat, it was normalized
and tested for chemical analysis trough direct reading spectrometer, metallographic
studies like micro structure, grain size and inclusion rating, hardness
in BHN, mechanical tests like UTS, YS, %EI and bend-rebend tests were
carried out. Test pieces were cut from each heat of 4 sets of rolled products
and each set was tested for microstructure, hardness. UTS, YS and %EI.
The results have been presented in tabular form in Table-2 for inclusion
rating and Table-3 through Table-8 for mechanical tests.
|
| |
| Some of the unique features of JVSL
COREX operation |
| |
|
Undersized iron ore (size 6-12mm)
is being charged directly into the COREX melter-gasifier. It was realized
that the surplus heat available at the top of the char bed (stable bed
inside melter-gasifier) could be utilized for reduction of iron ore fines.
Addition of iron bearing material via the coal line increases the hot
metal productivity, generates extra reduction gas for the shaft and helps
in controlling the process parameters more uniformly. On a monthly average
basis, maximum 15.5% of the total iron bearing material has been substituted
by iron ore fines addition.
|
|
| Oxygen distribution inside melter-gasifier |
|
During the startup of COREX Module-1,
the practice was to feed about 15-18% of the total oxygen through the
melter-gasifier dust burners and the balance trough the tuyeres. With
this operational practice, there had been some problems, such as high
sludge rate, sudden rise in pressure (pressure peaks), gas channeling
through the char bed, rise in melter-gasifier dome temperature, unstable
hot metal quality etc. With improved understanding of the process, the
oxygen amount through the dust burner was increased gradually and oxygen
through tuyeres was reduced correspondingly and positive results were
observed. Presently, about 25 - 30% of the total oxygen is passed through
dust burners and the balance through the tuyeres. In this process a major
share of the metallurgical reactions, such as, residual reduction, calcination
etc. are carried out in the upper part of the char bed which results in
stable char bed condition, reduction in sludge rate and better hot metal
quality.
|
| Selection of non-coking coals |
|
JVSL is importing coals from Australia, South Africa and
China. All these coals have been initially tested in the laboratory and
later found to be suitable for COREX operation. Over last two years of
operation, JVSL COREX has used more than ten different type of coals either
individually or as a blend of two or three types of coals. Wide ranges
of volatile matter (20-34%) and coal ash (9-12%) have been tried in CORER.
Additionally, other physico - chemical properties such as the strength
and the reactivity of the coal char also varied widely. A high volatile
coal is blended with low volatile coals so as to maintain the total volatile
content around 30%. On similar, lines, it is preferred to blend high ash
content, with low ash coal to maintain a moderate content in the coal
blend. The mean particle size of the coal blend has significant influence
on the process and is closely monitored besides other quality parameters.
|
| Recycling of various by products and
plant wastes |
|
|
The drive towards reduction in hot metal price has prompted
JVSL to adopt innovative measures for recycling of various by products
and plant wastes. Some of these are:
- Use of BOF Slag
- Mill scale
- Limestone and Dolomite fines
|
| TARGET AHEAD |
|
Recycling of various by products and
plant wastes |
|
At JVSL COREX, trials have been undertaken with indigenous coal. The trials had been taken place with unwashed coal from Singareni collieries. Though the percentage ash in indigenous coal was high due to low AI203 in ash of the selected coal, there was not much increase in slag rate with controlled proportion of indigenous coal in the coal blend. It was observed that about 10-15% of indigenous coal in the blend did not have any operational problems. The trials with other Indian coals will be conducted.
|
|
CONCLUSION
|
The performance of COREX process indicates brighter future
smelting-reduction process. JSVL has carried out a number of developments
within a short span of operation and is constantly striving for further
improvements. The present pace of developments would definitely pave the
way towards the lower cost steel production. |
| Steam injection
|
Steam injection which is practiced at POSCO,
is proposed to be introduced at JVSL in near future. The advantages will
be, increased raceway size and thereby improved distribution of gas flow
and decrease in RAFT, which will help in reducing frequency of tuyere burning.
Up to 100 gms of steam per ton of hot metal can be injected. |
| Use of waste plastics
|
Plastics having high calorific value (-10,000 kcal/kg) can reduce the fuel rate and can be directly fed with coal unlike in blast furnace where it is injected. This would be economical, as the expensive injection equipment will not be used. About 100 kg of plastics can be used per ton of hot metal. |
|